Micron Delays Construction Timeline for Semiconductor Fabs
Construction on Micron Technology’s semiconductor fabrication plants in Clay, New York, faces significant delays, according to a revised timeline included in the project’s approved Final Environmental Impact Statement (FEIS). The updated schedule indicates that while tree clearing will commence this year, the construction of four fabrication facilities, or fabs, will be postponed by several years to accommodate utility requirements.
Under the new timeline, the start of construction for Fab 1 is now set for the second quarter of 2028, with operations potentially beginning in the third quarter of 2030. This represents a two-year delay from the initial projections outlined in the Draft Environmental Impact Statement (DEIS). Similarly, the construction of Fab 2 will begin two years later than previously expected, with work starting in the last quarter of 2030 and operations not slated to commence until the final quarter of 2033, marking a three-year delay.
Extended Timeline for All Fabs
The timeline for Fab 3 has also shifted, with construction now beginning in the third quarter of 2035, a two-year postponement, while Fab 4’s completion has been pushed back by one calendar quarter, now expected by 2041. The revised construction schedule indicates that the overall process will take approximately 16 years and will be subject to the approval of necessary permits.
The FEIS highlights the impact of these delays on associated facilities. For instance, the construction of a childcare site will be rescheduled from 2026 to 2028, while the healthcare and recreation centers will now be initiated between 2030 and 2032. Additionally, securing warehouse space is now expected to occur by November 2028 due to the later start of wafer production.
Despite these adjustments, Micron anticipates that the final construction of the campus, including Fab 4, will still be completed by 2041. The facility is projected to reach full production by the end of 2045, creating over 9,000 permanent onsite operational jobs, according to the FEIS.
The revised timeline reflects Micron’s commitment to meeting utility needs while continuing to advance the development of its semiconductor production capabilities in Clay.
-
Top Stories1 month agoUrgent Update: Tom Aspinall’s Vision Deteriorates After UFC 321
-
Health1 month agoMIT Scientists Uncover Surprising Genomic Loops During Cell Division
-
Science4 weeks agoUniversity of Hawaiʻi Joins $25.6M AI Project to Enhance Disaster Monitoring
-
Top Stories1 month agoAI Disruption: AWS Faces Threat as Startups Shift Cloud Focus
-
Science2 months agoTime Crystals Revolutionize Quantum Computing Potential
-
World2 months agoHoneywell Forecasts Record Business Jet Deliveries Over Next Decade
-
Entertainment1 month agoDiscover the Full Map of Pokémon Legends: Z-A’s Lumiose City
-
Top Stories2 months agoGOP Faces Backlash as Protests Surge Against Trump Policies
-
Entertainment2 months agoParenthood Set to Depart Hulu: What Fans Need to Know
-
Politics2 months agoJudge Signals Dismissal of Chelsea Housing Case Citing AI Flaws
-
Sports2 months agoYoshinobu Yamamoto Shines in Game 2, Leading Dodgers to Victory
-
Health2 months agoMaine Insurers Cut Medicare Advantage Plans Amid Cost Pressures